Summary
The Agency approved early spending to bring CORE Construction aboard as Construction Manager at Risk while the new City Hall is still in design. CORE will handle cost estimating, constructibility reviews and Guaranteed Maximum Price development before the main construction contract.
At a glance
- Total mentions
- 2
- Last 30 days
- 0
Discussed at 1 meeting in the last 60 days; most recently Sep 28, 2026.
Impact analysis
The preconstruction contract commits $163,120; the full construction cost of the new City Hall has not been set.
Sparks residents, who will get a new City Hall developed with cost and schedule discipline built in from the design phase.
Mentions & discussions (2)
Sparks Redevelopment Agency Meeting — September 28, 2026
The Agency approved early spending to bring CORE Construction aboard as Construction Manager at Risk while the new City Hall is still in design. CORE will handle cost estimating, constructibility reviews and Guaranteed Maximum Price development before the main construction contract.
Sparks City Council — April 13, 2026 (Sparks City Council Meeting)
The Redevelopment Agency approved a $3.725 million architectural design contract for a new Sparks City Hall to replace the aging 1969 facility.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Sparks
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.